FBI Strong-Arms Trilogy Project
Submitted by Templar Titan on Mon, 04/19/2004 - 03:33.
FBI Strong-Arms Trilogy Project
(Federal Computer Week <http://www.fcw.com>
)
"After several deadline slips in the Trilogy modernization program, FBI officials have put some force behind the management of the contract," reports Federal Computer Week. "To improve the chances for the program's success, bureau officials have revised the agency's contracts with Computer Sciences Corp. (CSC), one of the vendors working on Trilogy, the FBI's effort to modernize its outdated information technology infrastructure. The systems integrator will face financial penalties if it does not complete the work by the new deadline, April 30."
[View article <http://www.fcw.com/fcw/articles/2004/0412/pol-fbi-04-12-04.asp> ]